Hospital of Adria

Modern hospital building for the city of Adria

  • Adria, Italia
  • Hospitals
  • Completed: 2013

€10M

Total investment

Highlights

  • accomplished in 450 days
  • state-of-the-art plant system
  • building on 5 levels

 

Description

Construction of a service building for the Adria hospital which connects the three buildings of the hospital complex via a series of tunnels and corridors.

The structure is built to be flexible over time with a regular 8×8 m grid made up of steel pillars and beams with a central core of the stairwells in reinforced concrete, with a windbreak function, and stairwell systems, with vertical distribution shafts to guarantee the connections with the equipment rooms on the top floor and the single rooms of the ground floor areas.

 

Companies involved

Sacaim Rizzani de Eccher Codest Division

The group

General contracting

Specialized contracting